The Project Fact Sheets

RING OF FIRE – REGIONAL DEVELOPMENT

Written by Canadian Indigenous Investment Forum | Dec 4, 2025, 2:55:02 PM

Project Spotlight

Ring of Fire Regional Development 

The Ring of Fire is one of Canada's most significant undeveloped mineral districts, located in the James Bay lowlands of Northern Ontario, approximately 540 kilometres northeast of Thunder Bay. The district contains deposits of chromite, nickel, copper, cobalt, platinum group metals, vanadium, and gold across an area with an active claim area described by the Ontario government as approximately 8,000 square kilometres. Multiple project proponents are advancing development, supported by government infrastructure commitments and Indigenous-led infrastructure programmes. 

In January 2025, the Impact Assessment Agency of Canada and 15 First Nations finalised the terms of reference for a co-led regional assessment of development activities and cumulative impacts across the district. The same month, Ontario and Aroland First Nation signed a Shared Prosperity Agreement providing over CAD $90 million for infrastructure and transmission line planning.

Sources: IAAC, Regional Assessment in the Ring of Fire Area; Ontario Government, Ring of Fire; CIM Magazine

 

Overview

The Ring of Fire comprises multiple mineral projects within the James Bay lowlands. The Ontario government has described an estimated mineral value of CAD $60 billion for the district. Development requires substantial infrastructure investment, including an all-season road network of more than 500 kilometres, a 230-kilometre transmission line, broadband connectivity, and community facilities.

The district spans the traditional territories of 15 First Nations, referred to by local First Nations as Kawana 'bi 'kag. Webequie First Nation and Marten Falls First Nation are co-proponents of the Northern Road Link, the segment connecting the broader road network to the mineral district.

Three principal project proponents are advancing exploration and development at various stages: Wyloo (Eagle's Nest nickel-copper-platinum group metals project), Juno Corp (exploration across approximately 5,796 square kilometres of claims), and several other companies, including New Age Metals and MetalQuest Mining, that have staked claim positions in the district since 2025.

Sources:  IAAC; Ontario Government; Juno Corp, January 2026

Key Facts

Category  Information 
Location  James Bay lowlands, Northern Ontario, approximately 540 km northeast of Thunder Bay 
Province Ontario 
Traditional Territories  15 First Nations (traditionally known as Kawana 'bi 'kag) 
Key Commodities Chromite, nickel, copper, cobalt, platinum, palladium, vanadium, gold
Ontario Infrastructure Commitment CAD $1 billion
Greenstone Transmission Line 230 km, 230 kV; Hydro One designated to construct; in-service target 2032
Regional Assessment Status Co-led by IAAC and 15 First Nations; conduct phase commenced January 2025; interim report submitted February 2026 

Sources: Ontario Government; IAAC Registry, Reference No. 80468; Hydro One, 28 January 2026

Development

The Ring of Fire has been under exploration and development planning since 2007. Noront Resources discovered the Eagle's Nest nickel-copper deposit in 2007 and the Blackbird chromite deposit in 2008. Cliffs Natural Resources subsequently acquired chromite properties, including Black Thor, Black Label, and a 70 per cent interest in Big Daddy, and spent approximately CAD $500 million on acquisition and development before indefinitely suspending the project in November 2013, citing infrastructure and regulatory obstacles. Noront acquired Cliffs' chromite properties in 2015. Wyloo, part of the Tattarang private investment group headquartered in Perth, Australia, completed its acquisition of Noront in April 2022, renaming it Ring of Fire Metals, and subsequently unified its operations under the Wyloo brand.

 Wyloo

Wyloo is advancing the Eagle's Nest project, a nickel-copper-platinum group metals underground mine containing over 20 million tonnes of measured, indicated, and inferred resources. The Impact Assessment Agency of Canada describes the project as producing approximately 3,000 tonnes of ore per day with an expected mine life of 12 to 15 years. In February 2026, the IAAC determined that Eagle's Nest would not be designated for a federal impact assessment. Wyloo's feasibility study is underway. The company has signed a memorandum of understanding with the City of Greater Sudbury for a downstream battery materials processing facility, with construction intended to follow the Eagle's Nest mine.

 Juno Corp

Juno Corp is a private, Ontario-based exploration company and the largest mineral claimholder in the Ring of Fire. As of January 2026, Juno holds approximately 29,956 claims covering 5,796 square kilometres, representing over 52 per cent of the district's mineral claims. In 2026, Juno commenced a CAD $20 million, 100-hole drilling programme described as the largest in the Ring of Fire in over a decade. Key exploration targets include the Vespa Critical Minerals Complex, covering titanium, vanadium, high-purity iron, scandium, and gallium, and gold discoveries at Big Thunder, Pluto, and North Edge. 

Sources: IAAC, Eagle's Nest Mine Project; Wyloo, About; Wyloo, Process; Globe and Mail, Cliffs chromite exit, 2015; Juno Corp, January 2026; Juno Corp, March 2026 

Development Stage (September 2026)

Status: Road infrastructure approvals secured; regional assessment in progress; mine projects in permitting and feasibility phases

  • The Webequie Supply Road (107 km) received provincial environmental assessment approval in June 2026 and the federal impact assessment decision statement on 25 June 2026. Construction is scheduled to commence June 2026
  • The Marten Falls Community Access Road (approximately 200 km) environmental assessment was submitted on 20 February 2026, with provincial review underway through 2026. The federal impact assessment decision statement was issued on 31 August 2026
  • The Northern Road Link, the connecting segment between the Marten Falls and Webequie roads, remains in the environmental assessment process; Ontario's accelerated plan targets construction commencing spring 2028
  • The Regional Assessment interim report was submitted to First Nations Chiefs and the Minister of the Environment, Climate Change and Nature in February 2026; the assessment remains in the conduct phase
  • The Impact Assessment Agency of Canada determined in February 2026 not to designate the Eagle's Nest mine for a federal impact assessment
  • Wyloo's feasibility study for Eagle's Nest is underway
  • Juno Corp commenced its 2026 drilling programme in March 2026

Sources:  Ontario, Webequie Supply Road; IAAC, Webequie Supply Road; Canada.ca, Marten Falls federal decision, 31 August 2026; Ontario, Marten Falls Community Access Road; Ontario, Northern Road Link; IAAC Registry, Regional Assessment; CBC, 26 June 2026 

Timeline

Date  Milestone 
2007  Noront discovers Blackbird chromite deposit 
November 2013  Cliffs Natural Resources indefinitely suspends Black Thor chromite project 
2015  Noront acquires Cliffs' Ring of Fire chromite properties 
8 October 2021  Ontario approves Terms of Reference for Webequie Supply Road and Marten Falls Community Access Road environmental assessments 
April 2022  Wyloo completes acquisition of Noront Resources 
3 March 2023  Ontario approves Terms of Reference for Northern Road Link environmental assessment 
20 January 2025  IAAC and 15 First Nations finalise regional assessment terms of reference 
28 January 2025  Ontario and Aroland First Nation sign Shared Prosperity Agreement (over CAD $90 million) 
28 January 2026  Ontario designates Hydro One to construct Greenstone Transmission Line 
30 January 2026  Webequie First Nation submits provincial environmental assessment for Webequie Supply Road 
20 February 2026  Marten Falls First Nation submits provincial environmental assessment for Community Access Road 
20 February 2026  IAAC determines Eagle's Nest will not be designated for federal impact assessment 
February 2026  Regional Assessment interim report submitted 
March 2026  Ontario releases accelerated road construction plan, five years ahead of prior schedule 
June 2026  Ontario gives provincial approval for Webequie Supply Road 
25 June 2026  Federal impact assessment decision statement issued for Webequie Supply Road 
August 2026  Anaconda and Painter Lake Road upgrades commence 
31 August 2026  Federal impact assessment decision statement issued for Marten Falls Community Access Road 
November 2030  Target opening of Webequie Supply Road and Anaconda/Painter Lake Roads
November 2031  Target opening of Marten Falls Community Access Road and Northern Road Link 
2032  Target in-service date for Greenstone Transmission Line 

Sources:  Ontario, Webequie Supply Road; Ontario, Marten Falls; IAAC, Eagle's Nest; Ontario accelerated plan, March 2026; Canada.ca, Marten Falls federal decision; Ontario, Aroland road upgrades, August 2026; Hydro One, Greenstone

Infrastructure

 Road Network

Ontario's accelerated plan, released in March 2026, comprises four road segments totalling more than 500 kilometres.

The Webequie Supply Road (107 km) will connect Webequie First Nation's airport to the McFaulds Lake area. The corridor is approximately 35 metres wide, accommodating a two-lane gravel surface industrial supply road with potential for future transmission lines and broadband. Webequie First Nation is the proponent. Provincial approval was granted in June 2026; the federal decision statement was issued on 25 June 2026. Construction is scheduled to commence June 2026, with opening targeted for November 2030.

The Marten Falls Community Access Road (approximately 200 km) will connect Marten Falls First Nation to the provincial highway system near Aroland and Nakina. Marten Falls First Nation is the proponent. The environmental assessment was submitted on 20 February 2026. The federal decision statement was issued on 31 August 2026. Under a November 2025 Community Partnership Agreement, Marten Falls First Nation receives up to CAD $39.5 million for community infrastructure. Construction is scheduled for August 2026, with opening targeted for November 2031.

The Anaconda and Painter Lake Roads connect Highway 643 to the proposed all-season routes leading toward the Ring of Fire. Upgrades commenced in August 2026 under the Aroland Shared Prosperity Agreement. Opening is targeted for November 2030.

The Northern Road Link is the connecting segment between the Marten Falls Community Access Road and the Webequie Supply Road, crossing the Attawapiskat River to reach the Ring of Fire mineral district. Marten Falls First Nation and Webequie First Nation are the co-proponents. The Terms of Reference were approved on 3 March 2023. The environmental assessment is under preparation. Construction is scheduled to commence spring 2028, with opening targeted for November 2031.

Sources:  Ontario, accelerated plan; CBC, 26 June 2026; IAAC, Webequie Supply Road; Ontario, Marten Falls; Canada.ca, Marten Falls federal decision; CPECN, Marten Falls agreement; Ontario, Aroland road upgrades; Ontario, Northern Road Link

Greenstone Transmission Line

On 28 January 2026, Ontario designated Hydro One to construct the Greenstone Transmission Line, a single-circuit 230 kV transmission line, designed to support a future second circuit, running approximately 230 kilometres from the existing East-West Tie near Nipigon Bay to a new switching station in or near Aroland First Nation. The line is expected to be in service by 2032 and will provide 350 to 700 MW of additional capacity in Northern Ontario. 

Seven First Nations along the Highway 11 corridor and around Lake Nipigon will have access to Hydro One's First Nations 50-50 Equity Partnership Model, providing the opportunity to invest in a 50 per cent equity stake in the transmission line component.

Sources: Hydro One, 28 January 2026; CBC, 28 January 2026; Northern Ontario Business, 28 January 2026

 Broadband Connectivity

The Matawa Broadband project is providing high-speed internet connectivity to northern communities.

Government Commitments

Ontario

Ontario has committed CAD $1 billion to Ring of Fire infrastructure. The 2026 Ontario Budget reiterated this commitment and called on the federal government to match or exceed it.

  • The Shared Prosperity Agreement with Aroland First Nation, signed 28 January 2025, provides over CAD $90 million: approximately CAD $70 million to advance route and design planning for the Greenstone Transmission Line, approximately CAD $20 million for local infrastructure projects, and CAD $2.27 million for a comprehensive community plan for Aroland
  • A Community Partnership Agreement with Marten Falls First Nation, signed November 2025, provides up to CAD $39.5 million for community infrastructure
  • An investment of CAD $61.8 million in the Geraldton Main Street Rehabilitation Project in the Municipality of Greenstone, announced September 2025, providing gateway road infrastructure for the Ring of Fire
  • Agreements with Webequie First Nation and Marten Falls First Nation valued at up to CAD $39.5 million each, to support road construction through their territories

In 2025, Ontario passed the Protect Ontario by Unleashing our Economy Act (Bill 5), which among other provisions empowers the government to create special economic zones intended to accelerate mining development. The Ring of Fire was announced as the intended first such zone.

Federal

The federal government co-leads the regional assessment through the Impact Assessment Agency of Canada. In December 2025, Ontario and the federal government signed a cooperation agreement to coordinate assessment processes and reduce regulatory duplication. The IAAC committed to completing reviews of the Webequie Supply Road and Marten Falls Community Access Road in 2026, and both projects subsequently received their federal decision statements in June and August 2026 respectively.

Federal programmes supporting Ring of Fire development include the Critical Minerals Infrastructure Fund, extended through the First and Last Mile Fund (CAD $1.5 billion, 2026 to 2030), and the Critical Minerals Sovereign Fund (CAD $2 billion over five years from Budget 2025).

Sources:  Ontario 2026 Budget; Northern Ontario Business, Aroland agreement; CPECN, Marten Falls agreement; ConstructConnect, Ontario accelerated plan; CBC, Greenstone; Canadian Mining Journal, Bill 5; GlobeNewswire, December 2025 cooperation agreement

Regulatory Status

The primary regulatory framework comprises several concurrent processes. The Regional Assessment, IAAC Reference No. 80468, is co-led by the IAAC and the 15 First Nations. The terms of reference were finalised on 20 January 2025. The conduct phase commenced in early 2025. The interim report was submitted in February 2026. The final report and recommendations remain pending. 

Individual infrastructure and mining projects proceed through their own environmental assessment and permitting processes. The Webequie Supply Road and Marten Falls Community Access Road have both received their federal and provincial approvals. The Northern Road Link is in the environmental assessment preparation phase. 

The IAAC determined in February 2026 that Eagle's Nest would not be designated for a federal impact assessment. 

Ontario's Bill 5, the Protect Ontario by Unleashing our Economy Act, 2025, introduced special economic zone provisions intended to accelerate development in the Ring of Fire.

Sources: IAAC Registry; IAAC, Eagle's Nest; Ontario, Webequie; Canada.ca, Marten Falls decision

Indigenous Leadership and Participation

The Ring of Fire spans the traditional territories of 15 First Nations. The following communities are the co-leads and participants in the regional assessment, as listed by the Impact Assessment Agency of Canada: Aroland First Nation, Attawapiskat First Nation, Constance Lake First Nation, Eabametoong First Nation, Fort Albany First Nation, Ginoogaming First Nation, Kashechewan First Nation, Long Lake #58 First Nation, Marten Falls First Nation, Missanabie Cree First Nation, Moose Cree First Nation, Neskantaga First Nation, Nibinamik First Nation, Webequie First Nation, and Weenusk First Nation. .

 Infrastructure Co-Proponents

Webequie First Nation and Marten Falls First Nation are co-proponents of the Northern Road Link and proponents of their respective community access and supply roads 

Aroland First Nation

Aroland First Nation signed the Shared Prosperity Agreement with Ontario on 28 January 2025. Aroland is positioned at the gateway to the Ring of Fire, 60 kilometres north of Geraldton on Highway 584/643. Chief Sonny Gagnon signed the agreement on behalf of Aroland.

Greenstone Transmission Line

Seven First Nations along the Highway 11 corridor and around Lake Nipigon, including Aroland First Nation, Animbiigoo Zaagi'igan Anishinaabek, Ginoogaming First Nation, Biinjitiwaabik Zaaging Anishinaabek, Bingwi Neyaashi Anishinaabek, Long Lake #58 First Nation, and Red Rock Indian Band, are participating in the Greenstone Transmission Line and will have access to Hydro One's 50-50 First Nations Equity Partnership Model.

Sources: IAAC, participant funding notice; CIM Magazine, Aroland agreement; Hydro One, Greenstone; Ontario ERO Notice 025-0660